Full SONA report can be found at http://www.gov.ph/sona/sona2008.pdf
Northrail Project
P61.91 Billion
Caloocan, Bulacan,
Pampanga
DOTC, NLRC
2011 • Phase 1 Section 1 (Caloocan-Malolos) is 9.67% accomplished with ongoing relocation of project-affected families
• Phase 1 Section 2 (Malolos-Clark) - feasibility study completed
37. Northrail-Southrail
Linkage ProjectP6.79 Billion
Caloocan, Alabang,
Calamba, Laguna
DOTC, PNR
• Phase 1 is 21.43% complete
• Phase 2- Philippine National Railways (PNR) is awaiting funding confirmation from the Export-Import Bank of Korea
38. Light Rail Transit (LRT)
Line 1 North ExtensionP6.32 Billion
Monumento, Caloocan
to North Avenue, Quezon
City
DOTC, Light Rail Transit
Authority (LRTA)
April 2010 • Notice to proceed for Packages’ A and B was issued on 28 May 2008.
Site inspection and mobilization for the two packages are ongoing.
• Bidding for Package C is being undertaken.
39. Metro Rail Transit (MRT)3 Capacity Expansion
US$67.50 Million
EDSA
DOTC, LRTA
2014 DOTC is looking into the procurement of refurbished light rail vehicles for Phase 1 while proposed Official Development Assistance (ODA) funding for Phase 2 is up for NEDA-ICC
deliberation.
A- 8
Project Completion Date Status(As of end-May 2008 or as stated)
40. MRT 7
US$1.24 BillionNorth Ave. to Tala Exit,
Bulacan
DOTC, LRTA
2013
DOTC, DOF, and NEDA are discussing the project’s Business Plan. The project is targeted to be completed by 2013.
41. LRT Line 2 Phase 2 (Line
2 East Extension to
Masinag)P10.32 Billion
Santolan LRT 2-Masinag,
Antipolo
DOTC, LRTA
Timeline to be determined LRTA is updating the project’s 2001 feasibility study and drafting the terms of reference for the procurement of the consulting services for the design/build scheme.
42. LRT Line 1 South
Extension Project
P36.20 Billion
Pasay City, Manila to
Bacoor, Cavite
DOTC, LRTA
June 2012
Proposals for the project’s implementation scheme are currently being evaluated by the newly created Project Review Team composed of the DOTC, LRTA, and the Provincial Government of Cavite.
43. Southrail Project Phase
1A
P15.31 Billion
Calamba, Laguna to Lucena
City, Quezon
DOTC, PNR
February
2010
While funding for the project is still being sourced, the President approved P1.55 Billion for the limited reconstruction of the railway to enable the resumption of train services to Bicol.
Showing posts with label Railway Update. Show all posts
Showing posts with label Railway Update. Show all posts
Wednesday, July 30, 2008
Tuesday, May 27, 2008
Philippine Railways Update! (May 2008)
Philippine National Railways
NEWS:
*** SUBJECT TO CONFIRMATION ***
With the Northrail project seemingly foundering, it comes with great sadness today, a report saying that work on the linkage project has been suspended indefinitely due to problems with relocation.
This is obviously tragic news for the country, but also quite strange. With so much clearing already having been done, most of it in areas the line hasn't yet been upgraded, its a wonder they don't keep upgrading these sections while the relocation works in the other areas in completed.
What was going to be President Gloria's greatest legacy to her country, is shaping up to be her biggest failure to those people she represents.
The Carmona branch may have been reopened to service, but this is also awaiting confirmation.
SOUTHRAIL REBUILD:
Phase I (Caloocan to Alabang) - Clearing Reportedly Suspended!
*** Trains operating between Tutuban-Alabang-San Pedro-Binan.
*** Media reported a train from Carmona killing a 14yo girl at Sucat during May. This would suggest the San Pedro to Caromna branch has reopened. This is subject to confirmation.
*** Services suspended Binan-Legaspi.
Phase II (Alabang to Calamba)Southrail Project - Work yet to commence.
Phase IA (Calamba-Lucena)Phase IB (Lucena-Legaspi) - Work yet to commence.
Phase II (Sorsogon Extension Matnog) - Work yet to commence.
PLANNED LINES:
Calamba to Batangas line rebuild - Work yet to commence.
Northrail
NEWS:
Despite advice that the project was to be proceeding full steam ahead, there has been little sign of work when visits were made.
NORTHRAIL REBUILD:
Caloocan to Malolos - Rebuild reportedly commenced full steam ahead January 2008.
Malolos to Clark - Rebuild reported to have commenced, no further advice.
PLANNED LINES:
Cabanatuan Line - No advice.
Cagayan Valley - No advice.
Panay Railway
Work has yet to commence on any railway building on Panay!
Iloilo City to Roxas City - No Advice*** There has yet to be movement in regards to anyone willing to finance this project.
Mindanao Railway
Work has yet to commence on any railway building in Mindanao!
Phase 1, Ist Segment (Cagayan de Oro-Iligan CityPhase 1, 2nd Segment (Cagayan de Oro-Gingoog City)
Phase 1, 3rd Segment (Iligan-Marawi City)
Phase 1, 4th Segment (Marawi City-Cotabato City)
Phase II (Surigao-Butuan)
Phase III (Davao City-Monkayo)
Phase IV (Zamboaga City-Dipolog City)
Phase V (Gagayan de Oro-Davao City)
Railway & Industrial Heritage Society
MUSEUM:
The Malagunlong Bridge in Tayabas, Quezon has been placed on the groups watchlist. It was built in 1840.
Paco station (proposed museum): No advice.
ROLLINGSTOCK:
Inspection tour made of rollingstock at Hondagua. One track car (speeder) identified for possible preservation.
GENERAL:
Efforts continue in order to be able to soon accept contributions and official memberships to the new society. Further details on this in future updates!
Locomotive Fleets
Remains virtually unchanged since last reported on the Philippine Railways SIG website!Thanks
Thanks to the following people and publications for information used in this update:
Jaime Tiongson
Harvey Smoller
Bill Sullivan
Wheel On Steel
Lubricated Flange Railway E-zine ( http://www.zelmeroz.com/lf)
The SIG would also like to wish a very speedy revovery to our mate Nick Buenafe!
Jaime Tiongson
Harvey Smoller
Bill Sullivan
Wheel On Steel
Lubricated Flange Railway E-zine ( http://www.zelmeroz.com/lf)
Tuesday, March 11, 2008
Philippine Railways Update! (March 2008)
A roundup of where things are at, information gained from personal emails, various forums and newspaper websites. Contributions are always very welcome.
Philippine National Railways
NEWS:
** By early March a section of track (southbound at Paco) had been relaid and ballasted, the northbound line remained untouched.
The reason why this one little isolated section being done is unknown, however as Hanjin's worksite is reportedly here we can probably assume they are to work outwards for here in both directions.
No advice recieved on the proposed, and more logical, complete closedown of services for a proper rebuild. Perhaps they do not wish to cause the service interuption.
SOUTHRAIL REBUILD:
Phase I (Caloocan to Alabang) - Clearing Continues!
*** Trains operating between Tutuban-Alabang-San Pedro-Binan.
*** Services suspended Binan-Legaspi and San Pedro-Carmona.
Phase II (Alabang to Calamba)Southrail Project - Work yet to commence.
Phase IA (Calamba-Lucena)Phase IB (Lucena-Legaspi) - Work yet to commence.
Phase II (Sorsogon Extension Matnog) - Work yet to commence.
PLANNED LINES:
Calamba to Batangas line rebuild - Work yet to commence.
Northrail
NEWS:
Rebuild continuing, no further advice on developments.
NORTHRAIL REBUILD:
Caloocan to Malolos - Rebuild commenced full steam ahead January 2008.
Malolos to Clark - Rebuild commenced.
PLANNED LINES:
Cabanatuan Line - No advice.
Cagayan Valley - No advice.
Panay Railway
Work has yet to commence on any railway building on Panay!
Iloilo City to Roxas City - No Advice*** There has yet to be movement in regards to anyone willing to finance this project.
Mindanao Railway
Work has yet to commence on any railway building in Mindanao!
Phase 1, Ist Segment (Cagayan de Oro-Iligan CityPhase 1, 2nd Segment (Cagayan de Oro-Gingoog City)
Phase 1, 3rd Segment (Iligan-Marawi City)
Phase 1, 4th Segment (Marawi City-Cotabato City)
Phase II (Surigao-Butuan)
Phase III (Davao City-Monkayo)
Phase IV (Zamboaga City-Dipolog City)
Phase V (Gagayan de Oro-Davao City)
Railway & Industrial Heritage Society
MUSEUM:
Apart from another site inspection of Paco no other advice forthcoming.
ROLLINGSTOCK:
No information on attempts to preserve rollingstock has been received.
Locomotive Fleets
Remain virtually unchanged since last reported on the Philippine Railways SIG website!THANKS:
Thanks to Jaime and 'Wheels on Steel' for information contained in this update!
Wednesday, February 20, 2008
Railway Rebuild Update!
The below diagram outlines the stages for the rebuild and estimated costs.
Further details appear on the "PhilippineRailways' Yahoogroup.
.
Further details appear on the "PhilippineRailways' Yahoogroup.
.
Labels:
Linkage Project,
Northrail,
Railway Update,
Southrail
Tuesday, February 5, 2008
Philippine Railways Update! (February 2008)
A roundup of where things are at, information gained from personal emails, various forums and newspaper websites.
Phase I (Caloocan to Alabang) - Clearing Continues!
*** Trains operating between Tutuban-Alabang-San Pedro-Binan.
*** Services suspended Binan-Legaspi and San Pedro-Carmona.
Phase II (Alabang to Calamba)Southrail Project - Work yet to commence.
Phase IA (Calamba-Lucena)Phase IB (Lucena-Legaspi) - Work yet to commence.
Phase II (Sorsogon Extension Matnog) - Work yet to commence.
Planned Lines
Calamba to Batangas line rebuild - Work yet to commence.
Caloocan to Malolos - Rebuild commenced full steam ahead January 2008.
Malolos to Clark - Rebuild commenced.
Planned lines
Cabanatuan Line - No advice.
Cagayan Valley - No advice.
*** There has yet to be movement in regards to anyone willing to finance this project.
Phase 1, 2nd Segment (Cagayan de Oro-Gingoog City)
Phase 1, 3rd Segment (Iligan-Marawi City)
Phase 1, 4th Segment (Marawi City-Cotabato City)
Phase II (Surigao-Butuan)
Phase III (Davao City-Monkayo)
Phase IV (Zamboaga City-Dipolog City)
Phase V (Gagayan de Oro-Davao City)
Philippine National Railways
Southrail RebuildPhase I (Caloocan to Alabang) - Clearing Continues!
*** Trains operating between Tutuban-Alabang-San Pedro-Binan.
*** Services suspended Binan-Legaspi and San Pedro-Carmona.
Phase II (Alabang to Calamba)Southrail Project - Work yet to commence.
Phase IA (Calamba-Lucena)Phase IB (Lucena-Legaspi) - Work yet to commence.
Phase II (Sorsogon Extension Matnog) - Work yet to commence.
Planned Lines
Calamba to Batangas line rebuild - Work yet to commence.
Northrail
Northrail RebuildCaloocan to Malolos - Rebuild commenced full steam ahead January 2008.
Malolos to Clark - Rebuild commenced.
Planned lines
Cabanatuan Line - No advice.
Cagayan Valley - No advice.
Panay Railway
Iloilo City to Roxas City - Work yet to commence.*** There has yet to be movement in regards to anyone willing to finance this project.
Mindanao Railway
Work has yet to commence on any railway building in Mindanao!
Phase 1, Ist Segment (Cagayan de Oro-Iligan CityPhase 1, 2nd Segment (Cagayan de Oro-Gingoog City)
Phase 1, 3rd Segment (Iligan-Marawi City)
Phase 1, 4th Segment (Marawi City-Cotabato City)
Phase II (Surigao-Butuan)
Phase III (Davao City-Monkayo)
Phase IV (Zamboaga City-Dipolog City)
Phase V (Gagayan de Oro-Davao City)
Railway & Industrial Heritage Society
Society was officially registered late last year, since then there has been no advice regarding developments.
Unofficial reports say that an inspection of the observation car at Hondagua (see earlier report) is on the cards.
----- ## ---- ## -----## ----- ## ----- ## ----- ## -----
Thanks to the following for information included in this updates.
Wheel On Steel (Skyscrapercity Forum), Robert O'Brien, Bill Sullivan
Philippine Star newspaper.
Unofficial reports say that an inspection of the observation car at Hondagua (see earlier report) is on the cards.
Locomotive Fleets
Remain virtually unchanged since last reported on the Philippine Railways SIG website!----- ## ---- ## -----## ----- ## ----- ## ----- ## -----
Thanks to the following for information included in this updates.
Wheel On Steel (Skyscrapercity Forum), Robert O'Brien, Bill Sullivan
Philippine Star newspaper.