Full SONA report can be found at http://www.gov.ph/sona/sona2008.pdf
Northrail Project
P61.91 Billion
Caloocan, Bulacan,
Pampanga
DOTC, NLRC
2011 • Phase 1 Section 1 (Caloocan-Malolos) is 9.67% accomplished with ongoing relocation of project-affected families
• Phase 1 Section 2 (Malolos-Clark) - feasibility study completed
37. Northrail-Southrail
Linkage ProjectP6.79 Billion
Caloocan, Alabang,
Calamba, Laguna
DOTC, PNR
• Phase 1 is 21.43% complete
• Phase 2- Philippine National Railways (PNR) is awaiting funding confirmation from the Export-Import Bank of Korea
38. Light Rail Transit (LRT)
Line 1 North ExtensionP6.32 Billion
Monumento, Caloocan
to North Avenue, Quezon
City
DOTC, Light Rail Transit
Authority (LRTA)
April 2010 • Notice to proceed for Packages’ A and B was issued on 28 May 2008.
Site inspection and mobilization for the two packages are ongoing.
• Bidding for Package C is being undertaken.
39. Metro Rail Transit (MRT)3 Capacity Expansion
US$67.50 Million
EDSA
DOTC, LRTA
2014 DOTC is looking into the procurement of refurbished light rail vehicles for Phase 1 while proposed Official Development Assistance (ODA) funding for Phase 2 is up for NEDA-ICC
deliberation.
A- 8
Project Completion Date Status(As of end-May 2008 or as stated)
40. MRT 7
US$1.24 BillionNorth Ave. to Tala Exit,
Bulacan
DOTC, LRTA
2013
DOTC, DOF, and NEDA are discussing the project’s Business Plan. The project is targeted to be completed by 2013.
41. LRT Line 2 Phase 2 (Line
2 East Extension to
Masinag)P10.32 Billion
Santolan LRT 2-Masinag,
Antipolo
DOTC, LRTA
Timeline to be determined LRTA is updating the project’s 2001 feasibility study and drafting the terms of reference for the procurement of the consulting services for the design/build scheme.
42. LRT Line 1 South
Extension Project
P36.20 Billion
Pasay City, Manila to
Bacoor, Cavite
DOTC, LRTA
June 2012
Proposals for the project’s implementation scheme are currently being evaluated by the newly created Project Review Team composed of the DOTC, LRTA, and the Provincial Government of Cavite.
43. Southrail Project Phase
1A
P15.31 Billion
Calamba, Laguna to Lucena
City, Quezon
DOTC, PNR
February
2010
While funding for the project is still being sourced, the President approved P1.55 Billion for the limited reconstruction of the railway to enable the resumption of train services to Bicol.
No comments:
Post a Comment